HALLWAY
-Removal of existing front door
-Install wooden front door
KITCHEN
-Removal of two built in storage cupboards
-Removal of kitchen units, counters and tiles
-Removal of backdoor
-Block up back door in Air Crete blocks
-Install Kitchen units and worktop
-Install Glass Tiles above kitchen counters in a

'  Herringbone' Pattern one side and

'  Stacked Vertical' Pattern on the other
-Over-tack 9.5mm plasterboard to ceiling
-Apply finishing plaster to ceiling
-Install engineered wood flooring
-Demolish utility room/ Outhouse
DINING ROOM:
-Modify Staircase and construct under stairs

  storage unit beneath
-Install new bannister rails with white wooden

  square spindles
-Remove existing window unit
-Install 4ft patio door in place of existing

  window unit adjusting the opening if necessary
-Replacement of skirting with OGEE mould
-Install engineered wood flooring
FIRST FLOOR LANDING
-Adjust and add additional joists where necessary
-Renew any floorboards where necessary
-Widen loft hatch
-Over-tack ceiling in 9.5mm plasterboard
-Apply finishing plaster to ceiling
-Install new banister rails with white wooden

  square spindles
-Replace skirting board with OGEE mould
-Install Engineered oak flooring
UPSTAIRS HALLWAY (Leading to office)
-Over-tack Ceiling In 9.5mm plasterboard
-Apply finishing plaster to ceiling

 

PROJECT LEAD:
TRADES:

 

 

PLUMBER:             
ELECTRICAN: 

Karl Johnson

Jae Johnson, Karl Johnson, Tony Godden

 

Burt Warren
Gareth Heath

LOFT
-Install timber stud partition between the adjacent property in the loft space
-Apply Thermoguard Smoke & Flame Retardant Dualcoat to timbers
-Install CERAMIC FIBRE BLANKET 1260°C
-Install HT-HIGH TEMPERATURE PLASTERBOARD (A1 EN 13501-1:2002)
-Apply Mapei Mapeflex Firestop 1200°C High Temperature Grout to joints to create sealed membrane
LIVING ROOM
-Build partition wall incorporating a stained glass panel and 'bookcase wall' between dining room and living room
-Install wooden internal door within the newly created partition
-Replace skirting boards with OGEE mould
-Install engineered wood flooring
MAIN BEDROOM
-Remove plaster to expose joists to the left side of the door
-Remove existing wall surface to expose brickwork on Window Wall/Alcoves/Right side of door/ Half of chimney breast
-Install 12.5mm plasterboard to exposed brickwork and joists to create wall surface
-Prepare remaining walls and ceiling for plastering
-Apply additional coat of plaster on newly created wall surfaces
-Apply finishing plaster to walls and ceiling
-Replace skirting board with OGEE Mould
-Install coving to match existing
-Install wooden internal door
OFFICE
-Install wooden internal door
-Install coving to match existing
-Install engineered wood flooring
SPARE BEDROOM
-Remove plaster to expose joists on door wall
-Remove existing wall surface to expose brickwork on wall opposite door
-Install 12.5mm plasterboard to exposed brickwork and joists to create wall surface
-Over-tack 9.5mm plasterboard to ceiling
-Apply finishing plaster to 4 walls and ceiling
-Replacement of skirting boards with OGEE mould
-Install wooden internal door